Australia’s data centre pipeline is big, but it’s leaking
Nov 25 , 2026
On paper, Australia’s data centre pipeline has never looked stronger.

The number of projects in the National Energy Market (NEM) connection process have more than doubled in a year from 97 to 225, and their proposed capacity has climbed from 38 GW to 67 GW. The surge is being driven by cloud migration and AI workloads, with hyperscalers and global operators competing for sites close to the network and fibre hubs of Sydney and Melbourne.
The Australian Energy Market Operator (AEMO)’s 2026 Electricity Statement of Opportunities (ESOO) forecasts data centre consumption in the NEM to grow nearly seven-fold, from about 5 TWh in 2025-26 to around 34 TWh by 2035-36, taking it from 2.8% of NEM operational consumption to 13% in 10 years.
To put it in perspective, that’s nearly as much electricity as every home in NSW and Victoria draws from the grid today (~38 TWh).
More than 40% of data centre projects since 2025 have been either cancelled or delayed, and around 36% of projects on AEMO’s 2025 list have since been cancelled.
Cancellations happen at every stage of development. Even with a signed connection agreement in place (which is typically regarded as proof a project is real), more than 30% of committed projects failed to launch.
This has impacts up and down the line.
Every stalled project ties up network planning effort, holds connection capacity others could use, and leaves landowners and investors carrying the cost of an asset that never earns revenue.
The questions are obvious.
For investors, landowners, networks and governments, the question is how to tell which projects will succeed.
For developers, it is how to make sure their project is one of them.

With such a steep demand, the market is seeing a huge upside. Underpinned by assumptions of instant revenue and streamlined approvals, some projects are failing to live up to the promises they made to investors.
There are four critical elements which provide a guide for the success or failure of a data centre project:
Grid capacity in the established hubs is being taken up fast.
In Western Sydney, connection agreements have been signed for 1.5 GW of new data centre demand. In Victoria, AusNet is currently assessing more than 10 GW of data centre connection requests, enough to push demand past the state’s current supply if they all went ahead.
The challenge is ensuring power supply can be secured and paid for.
Even well-backed, fully contracted projects are exposed, as recent power delays in Melbourne have shown.
When energisation slips, operators can be heavily impacted through deferred revenue, downgraded guidance and a sharp loss of investor confidence.
Little wonder then, the Commonwealth is currently drafting legislation targeted for early 2027, which will see large data centres required to underwrite their own power supply.
In May this year, a developer withdrew a 120 MW proposal in Perth after almost 1,900 public submissions were received, most of them objections, which resulted in the council recommending the project didn’t proceed. With no council approval, the project becomes technically unviable with project owners looking to move sites to find faster ways to market.
As governments, councils and communities become more and more aware of the impact and resource requirements of data centres, the need to engage faster and more deeply is increasingly apparent.
The rules are changing.
In a recent article in the Australian Financial Review, Robin Kuhda, CEO of AirTrunk, noted the US midterm election debate is accelerating the shift of data centre investment to Asia.
There is an opportunity for Australia to attract a greater share of these investments. However, projects need to meet a high standard, and governments have to back those projects that meet the bar.
At the same time, investors require confidence that projects meeting these standards can progress through transparent and predictable approvals processes. Uncertainty, inconsistent decision-making or prolonged delays can undermine Australia’s competitiveness in the global race for digital infrastructure investment.
“It’s right for governments to check claims about water, energy, noise and emissions against the evidence, and explain what safeguards are in place and how they will be monitored.” (Robin Khuda, AFR, 16 November, 2026)
The proposed Kurri Kurri Data Centre development in NSW highlights this balance. Located on the site of a former aluminium smelter, the project has incorporated industrial land reuse, commitments regarding energy supply and extensive community consultation. The project demonstrates both the opportunities and increasing scrutiny facing large-scale data centre developments across Australia.

Different policies in different places
The challenge for developers and investors is the variations in requirements from state to state. A site that clears the bar in one state may not clear it in another, and a project designed to today’s rules may need rework before it is approved.
Take the differing policies on power as one example.
The Commonwealth wants binding national standards that require new data centres to be backed by renewables, but the states are split.
NSW has already gone further, with guidelines that expect new data centres to contract new renewable generation equal to 100% of their annual demand.
Queensland and the Northern Territory have refused to sign up to a renewables requirement, with Queensland pushing for data centres to be powered by its state-owned coal and gas resources.
Canberra says there will be no carve-outs. How this lands is still unresolved.
Hyperscale developers are demanding certainty.
AEMO’s forecasting now uses project status, connection status and developer size to predict which projects are likely to progress. This provides a handy guide for investors. In the not-so-distant past, the excitement around the potential of data centres meant projects with a small sponsor, without a capital partner, without an anchor tenant and business cases built on Day One capacity were still being considered.
This is not the case today. Most projects without a compelling business case are less likely to proceed.
Attrition is high. Optimism alone is not enough.
Hyperscale customers want certainty on power, timing and room to expand. These customers are prepared to commit to the sites that can show it. Without this commitment, speculative projects are struggling to raise capital.
The expectation is that attrition will stay high before it falls.
However, this isn’t a sign the data centre boom is failing. Rather, the attrition rates are the pipeline sorting deliverable projects from the rest.
Australia’s data centre boom remains real, but success will increasingly depend on the ability to secure power, earn community support, navigate policy requirements and demonstrate genuine project readiness.

The risks data centres are currently facing can be planned for. The projects that will stay in the pipeline will be ones able to answer the hard questions early, before major capital is committed. The lessons to be learned are clear.
Energy and planning are two of the biggest hurdles, and MBB can help on both.
MBB has managed the commercialisation of assets and transactions across the Renewable Energy Zones (REZs) for EnergyCo and has established relationships with Transmission Network Service Providers (TNSPs) and energy developers. This experience positions MBB to help data centre developers secure capacity, line up new generation and meet tightening renewable energy requirements.
We understand where network capacity really exists, what it will cost to unlock, and how to structure generation and firming so a project’s power story holds up with networks, regulators and investors.
MBB can help developers navigate the fast-moving approvals and policy landscape. We understand the importance of social licence and can apply lessons learned on some of Australia’s largest infrastructure projects. MBB’s market intelligence work has also mapped the national hot spots where new data centres are most likely to avoid approval challenges.
If you’re assessing a site or considering an investment in the Australian data centre market, get in touch with MBB to discuss the opportunities and risks shaping the sector.